2019 - MOSAIC FERTILIZANTES P&K LTDA - MINA DE TAQUARI VASSOURAS

Preparation of a Basic and Detailed Project for a water reservoir to be used as a counterweight (using water ballast), positioned in the bottom section of the metal frame of one of the Skips in Shaft I at the Taquari Vassouras Mine. The counterweight with water ballast is used for the eventual removal of personnel from the bottom of the mine (balanced operation in the Skips), in the event of a power failure or similar problems that prevent the normal operation of the Friction Winder.

2016 / 2017- NEXA RESOURCES (VOTORANTIM METAIS) - VAZANTE MINE

Design of a new personnel transportation cage, selection and sizing of accessories for anchoring and tensioning the handlebars.

2016 / 2017 - ANGLOGOLD ASHANTI CÓRREGO DO SÍTIO MINERAÇÃO S.A.

Various projects for the Cuiabá mine and the Córrego do Sítio mine:

  • Basic and Detailed Design of Skip with bottom discharge, payload 8.5t, for the Cuiabá Shaft.
  • Basic and Detailed Design of the Divider Chute for the Cuiabá Shaft Charging Station.
  • Basic and Detailed Design for the installation of a Shoe Feeder for the Cuiabá Shaft Charging Station.

These are some of our success stories in engineering projects in mining and metallurgy. Our 25 years of experience in the field demonstrate our efficiency and our dedication to every detail in the different projects we develop. Want to learn more about our services? Get in touch with our team of engineers today.